Educational Facilities • Case Study Record

Construction of Rieger Park Primary School Facility

Statutory health and safety agency for the construction of a 28-classroom modern primary school with early childhood development centre, administration building, and sports facilities.

Discuss a Similar Project
Gauteng Department of Infrastructure Development (GDID)Client / Contracting Authority
R90 MillionContract / Capital Project Value
Pr. Construction Health and Safety Agent (SACPCMP CHSA)Diba BES Appointed Role
Statutory RolePr. Construction Health and Safety Agent (SACPCMP CHSA)
Client OrganisationGauteng Department of Infrastructure Development (GDID)
LocationBoksburg / Ekurhuleni, Gauteng
Delivery TimelineMar 2022 – Nov 2023

Strategic Engineering & Safety Delivery

The Challenge & Diba BES Solution

How Diba BES structured risk management protocols, contractor oversight, and statutory compliance to safeguard project delivery.

The Operational Challenge

Executing fast-track construction in an urban township environment with high community interest and traffic density.

Diba BES Strategic Response

  • Instituted strong community security perimeters, daily traffic marshaling, and strict access control for all heavy vehicle deliveries.

Approved Scope of Work

Key Statutory Deliverables & Engineering Scope

Detailed breakdown of specialized safety agency, risk assessments, inspections, and contractor governance tasks performed on site.

Client safety specification and contractor baseline risk assessments
Double-storey concrete slab, brickwork, and roof truss installation monitoring
Contractor safety file approvals and monthly DEL compliance audits

Quantified Outcomes & Delivery Impact

Measurable Results Backed by Verified Evidence

Documented performance metrics, zero-harm milestones, and statutory audit achievements recorded across this project.

01

Completed on schedule with Zero Lost Time Injuries across 450,000 man-hours

Verified Evidence
02

Delivered world-class learning facilities for over 1,000 urban learners

Verified Evidence

Stakeholder Governance & Standards

Technical Specifications & Engineering Partners

Client Contact / DirectorateGDID Infrastructure Delivery Unit
Procurement / Program CategoryGauteng Smart Schools Programme
Delivery MandatePr.CHSA Statutory Agent
Statutory Standards Complied
Construction Regulations 2014OHS Act 85/1993