Design-stage risk discussion register

Record design-stage H&S issues for the person authorised to decide the design response.

This register records an issue, its drawing or activity reference, the design decision owner and the outcome. It does not authorise a design change.

Worked example

The illustrative row asks about access for a future maintenance activity. The design authority determines the response using the relevant information; the register records that decision and any information to pass to later stages.

Use the resource

Keep the drawing revision visible and update the link when the design changes. Record unresolved questions and the next review point. Do not mark the issue closed solely because it was discussed in a meeting.

Worked record

Illustrative example — replace with verified information
Issue IDDrawing/activity referenceQuestionDecision ownerResponse evidenceNext-stage informationStatus
Example D-01Concept drawing A / maintenance accessHow is maintenance access addressed?Appropriate designerPendingTo be determined from responseOpen

How to use it

  1. Identify the activity and design reference.
  2. Record the question and missing information.
  3. Refer it to the appropriate authority.
  4. Link the response and later-stage information.

Your working record

Enter your information, then download a copy to keep it. Entries stay in this tab and are not saved automatically.

Complete the fields that apply to your requirement
Issue IDDrawing/activity referenceQuestionDecision ownerResponse evidenceNext-stage informationStatus

Blank record

Download a blank copy for offline reference or printing. Complete the editable record above to save your entries.

Download blank record

Related guidance and resources

Source context

Source context checked 6 October 2026. Examples are illustrative.